SAN DIEGO-Calpine Corp. and PG&E Corp. have reached an agreement for Calpine to acquire rights to build a 500-megawatt power plant in the South San Diego County community of Otay Mesa.

Under the terms of the agreement, San Jose-based Calpine will build, own and operate the Otay Mesa Generating Project, and PG&E’s National Energy Group will contract for up to 250 megawatts of the project’s output. In a joint statement, the two companies say they hope to bring the project on-line as soon as possible, providing much-needed electricity supplies to Southern California. Both companies ultimately will sell power from the plant to the California market.

The project “will be the first new power plant built in San Diego County in almost 30 years,” says Thomas B. King, president/CEO of the western region of PG&E’s National Energy Group.

“As we saw last summer, when a shortage in generating capacity led to high prices for consumers, there is a clear need for new generating capacity in the region,” he adds.

The project will be located within a 46-acre property on the eastern portion of Otay Mesa, near the base of the San Ysidro Mountains, about 1.5 miles from the Mexican border. King says PG&E and Calpine will work closely with regulators to move the project forward and meet the mid-2003 target date for making the facility operational.

“This project will improve the supply-demand balance in San Diego’s electricity market and will maintain the region’s environmental quality,” adds Calpine VP Peter Camp. “Otay Mesa is an important part of Calpine’s plans to rapidly develop clean, economic sources of electricity for Californians.”

The Otay Mesa facility will be fueled with natural gas and include state-of-the-art emission control equipment and water conservation technology.

Under the terms of its agreement, PG&E will complete the process of licensing the plant. The project is in the final stages of review by the California Energy Commission, which is expected to decide early next year whether to issue a construction license. Once the project is licensed, ownership will be transferred to Calpine. Construction is expected to begin in the third quarter of 2001.

Want to continue reading?
Become a Free ALM Digital Reader.

Once you are an ALM digital member, you’ll receive:

  • Unlimited access to GlobeSt and other free ALM publications
  • Access to 15 years of GlobeSt archives
  • Your choice of GlobeSt digital newsletters and over 70 others from popular sister publications
  • 1 free article* every 30 days across the ALM subscription network
  • Exclusive discounts on ALM events and publications

*May exclude premium content
Already have an account?


NOT FOR REPRINT

© 2024 ALM Global, LLC, All Rights Reserved. Request academic re-use from www.copyright.com. All other uses, submit a request to [email protected]. For more information visit Asset & Logo Licensing.

GlobeSt

Join GlobeSt

Don't miss crucial news and insights you need to make informed commercial real estate decisions. Join GlobeSt.com now!

  • Free unlimited access to GlobeSt.com's trusted and independent team of experts who provide commercial real estate owners, investors, developers, brokers and finance professionals with comprehensive coverage, analysis and best practices necessary to innovate and build business.
  • Exclusive discounts on ALM and GlobeSt events.
  • Access to other award-winning ALM websites including ThinkAdvisor.com and Law.com.

Already have an account? Sign In Now
Join GlobeSt

Copyright © 2024 ALM Global, LLC. All Rights Reserved.